MMK completed comprehensive hot tests of the aspiration systems of blast furnace No. 3

Mariupol Metallurgical Plant named after Ilyich (MMK, Donetsk region), a member of Metinvest Group, has completed comprehensive hot tests of new and reconstructed aspiration systems of blast furnace (BF) No. 3, investments in the environmental project amounted to more than $ 31 million.

According to the company’s press release on Thursday, all processes are fine-tuned, the equipment is operating at design capacity.

It is specified that the design, construction of new and reconstruction of the existing treatment equipment at DP-3 continued 19 months. The start-up of the aspiration units of the casting yard and the bunker rooms in test mode was carried out in conjunction with the start-up of DP No. 3 after overhaul in February.

The effectiveness of the applied technology is confirmed daily. New aspiration installations ensure residual dust content, which is two and a half times lower than Ukrainian standards, and the captured dust is sent daily for processing as recyclable materials.

“All major changes do not occur suddenly and abruptly, but gradually. Step by step. Metinvest is fulfilling its obligations and continues to implement the program of environmental modernization of the production facilities of the Mariupol iron and steel plants project by project, “said the General Director of MMK. Ilyich Taras Shevchenko, quoted by the press service.

MMK im. Ilyich is part of the Metinvest Group, the main shareholders of which are SCM Group (71.24%) and Smart Holding (23.76%), jointly managing the company.

Metinvest Holding LLC “- the management company of the Metinvest group.